AECL Nuclear Refurbishment Losses Quantified

The attached news report is the first time I have seen the losses being sustained by the federal government on Candu nuclear refurbishments quantified. Bruce Power, NB Power and Korea Electric power are receiving refurbishment services from AECL at far below cost. The news report indicates: “The Crown corporation lost $413 million on refurbishment projects …

Continue reading ‘AECL Nuclear Refurbishment Losses Quantified’ »

AECL: Jim Flaherty’s Atom Splitting Headache

This link: Jim_Flaherty_s_Atom_Splitting_Headache is the slide deck  originally prepared for a lecture presented to U of T EngSci ESC 203, “Engineering, Society and Critical Thinking” October 26, 2010. EngSci students are specifically invited to send in comments or questions, as are any other interested readers. Many thanks again to Lisa Romkey, the instructor for ESC 203, for the …

Continue reading ‘AECL: Jim Flaherty’s Atom Splitting Headache’ »

Upcoming TV Appearance: CFTO News re. Ontario Nuclear Delay

Bruce Power announced today a delay in returning two reactors to service. The reactors are currently undergoing a refurbishment of their respective reactor cores. Until today, the reactors were to be in service in mid to late 2011. The new dates have been pushed into 2012. Consumers will benefit in the short term as the …

Continue reading ‘Upcoming TV Appearance: CFTO News re. Ontario Nuclear Delay’ »

Update on AECL’s Commercial Disaster Happening in New Brunswick – October 2010

AECL has announced that it will re-remove the full complement of new calandria tubes that it had previous installed in the Point Lepreau reactor. Here is the very thin NB Power press release, a CBC news story with some useful history and context, and a Telegraph Journal newspaper article wherein I encourage New Brunswick to …

Continue reading ‘Update on AECL’s Commercial Disaster Happening in New Brunswick – October 2010’ »

Bruce Power CEO Discussing Failure of Ontario’s New Nuclear Procurement (2009)

Proceedings of the Standing Senate Committee on Energy, the Environment and Natural Resources Issue 7 – Evidence – June 1, 2010 OTTAWA, Tuesday, June 1, 2010 The Standing Senate Committee on Energy, the Environment and Natural Resources met this day at 5:10 p.m. to study the current state and future of Canada’s energy sector (including …

Continue reading ‘Bruce Power CEO Discussing Failure of Ontario’s New Nuclear Procurement (2009)’ »

Comments on AECL’s Federal Budget Allocations

AECL has been allocated $300 million for fiscal 10/11 on a cash basis in the federal budget. Given AECL’s track record in recent years of securing unbudgeted top-up payments through the year, taxpayers may well see greater cash losses this year. The stipulation in the budget that the funds are provided on a “cash basis” suggests that …

Continue reading ‘Comments on AECL’s Federal Budget Allocations’ »

Praise for OPG’s Decision to Forego Retubing Pickering B

Attached is a transcript of a brief interview with CH TV February 10, 2010 for the show “Live at 5:30” hosted by Mark Hebscher and Donna Skelly. In the interview, I praise OPG’s decision to not retube Pickering B. I also question why Samsung does not show up on the Ontario government’s official lobbyist registry. …

Continue reading ‘Praise for OPG’s Decision to Forego Retubing Pickering B’ »